A ship generator is a machine set that produces the electrical power for a vessel. A ship generator consists of a prime mover, usually a four-stroke diesel engine called the auxiliary engine, and an alternator that the engine drives. The alternator supplies three-phase alternating current to the main switchboard.

Class rules require enough generating sets to carry the essential load with any one set in reserve. A separate emergency generator outside the engine room takes over the safety services when the main supply fails.

Key facts

AttributeValue
Recommended low voltages400 V, 440 V and 690 V three-phase (IEC 60092-201, Table 3)
Recommended high voltages3.3 kV, 6.6 kV and 11 kV three-phase (IEC 60092-201, Table 3)
Frequency50 Hz or 60 Hz
Steady voltage held by the AVRWithin ±2.5% of rated voltage; ±3.5% for emergency sets (ABS 4-8-3/3.13.2)
Frequency limits of the governor±5% permanent; ±10% transient with recovery in 5 seconds (IACS UR M3)
Load sharing in parallelWithin 15% of the rated power of the largest set, or 25% of the individual set, whichever is less (IACS UR M3)
Reverse power trip, diesel sets8% to 15% of rated power (ABS 4-8-2/9.11.4)
Emergency generator on loadNot more than 45 seconds after loss of main power (ABS 4-8-2/5.9)
Diagram of a ship generator showing the auxiliary engine, exciter, stator, AVR and circuit breaker in order, with governor and AVR roles
The governors share the active load in kW, and the AVRs share the reactive load in kVAr.

What is a ship generator?

A ship generator is a diesel generator set that converts fuel energy into electrical energy for the ship. The diesel engine turns the alternator at a constant speed. The alternator feeds the main switchboard, and the main switchboard distributes power to pumps, fans, compressors, lighting, navigation equipment and galley equipment.

The complete set is also called a diesel generator (DG) or genset. The main engine drives the propeller, and the auxiliary engine drives the alternator.

What are the parts of a ship generator?

The parts of a ship generator are the auxiliary engine with its governor, the alternator with its stator, rotor and exciter, the automatic voltage regulator, the generator circuit breaker and the protection relays. The engine and the alternator are normally mounted on one base frame and joined by a coupling.

PartFunction
Auxiliary engine (prime mover)Four-stroke diesel or dual-fuel engine that turns the alternator at constant speed
GovernorControls the fuel supply, holds the speed and so holds the frequency
StatorFixed three-phase winding in which the output voltage is induced
RotorRotating field magnet fed with direct current
ExciterSupplies the direct current for the rotor field; a rotating exciter or a static exciter
Automatic voltage regulator (AVR)Adjusts the excitation current to hold the terminal voltage
Generator circuit breakerConnects the alternator to the switchboard busbars and opens on a fault
Protection relaysTrip the breaker on overcurrent, reverse power and undervoltage

The ABS Marine Vessel Rules, Part 4 require an automatic voltage regulator for each generator.

What are the types of generator on a ship?

The types of generator on a ship are the diesel generator, the shaft generator, the steam turbine generator and the emergency generator. The diesel generator is the standard main source of power. The other types supply power at sea from the main plant or supply the safety services after a blackout.

TypeDriven byTypical use
Diesel generatorAuxiliary engineMain source of electrical power at sea and in port
Shaft generatorMain engine or propeller shaftPower at sea; a frequency converter holds voltage and frequency at variable shaft speed
Turbine generatorSteam turbineShips with a steam plant
Emergency generatorSmall independent diesel engineEmergency lighting, communication and other safety services after a blackout

How does a ship generator make electricity?

A ship generator makes electricity by electromagnetic induction. The auxiliary engine rotates a magnetised rotor inside the stator winding. The moving field induces a three-phase voltage in the stator. The governor fixes the frequency through the engine speed, and the automatic voltage regulator fixes the voltage through the rotor field current.

  1. The engine starts and the governor brings the engine to rated speed.
  2. The exciter supplies direct current to the rotor winding, and the rotor becomes a rotating magnet.
  3. The rotating field induces a three-phase voltage in the stator winding.
  4. The AVR measures the terminal voltage and raises or lowers the excitation current.
  5. The generator circuit breaker closes and connects the alternator to the busbars.
  6. The governor adds fuel as the load rises, so the speed and the frequency stay constant.

The frequency in hertz equals the number of poles multiplied by the speed in rpm, divided by 120. A 10-pole alternator at 720 rpm gives 60 Hz, and an 8-pole alternator at 750 rpm gives 50 Hz. Speeds of 720, 750, 900 and 1,000 rpm on the Wärtsilä generating set range follow from this relation.

What voltage and frequency does a ship generator supply?

A ship generator supplies three-phase alternating current at 50 Hz or 60 Hz. IEC 60092-201 recommends nominal voltages of 400 V, 440 V and 690 V for low-voltage systems and 3.3 kV, 6.6 kV and 11 kV for high-voltage systems. A 440 V, 60 Hz system is a common choice on cargo ships.

The values come from Table 3 of IEC 60092-201:2019. ABS defines high voltage as above 1,000 V up to and including 15 kV. A Massachusetts Maritime Academy text on shipboard electric systems states that ships use high voltage, typically 3.3 kV, 6.6 kV or 11 kV, for motors of 400 kW or more, such as propulsion motors and thrusters.

How are ship generators synchronised and run in parallel?

Ship generators are synchronised by matching the incoming generator to the live busbars before the breaker closes. The incoming generator must have the same voltage, the same frequency, the same phase sequence and the same phase angle as the busbars. A synchroscope or synchronising lamps, which ABS requires on the switchboard, show the moment when the phase angles match.

The usual manual sequence is below. A power management system performs the same steps automatically on many ships. The ship's own procedure and the maker's manual take priority.

  1. Start the incoming set and let the speed and the voltage settle.
  2. Match the generator voltage to the busbar voltage and switch on the synchroscope.
  3. Adjust the governor so that the incoming frequency is slightly above the busbar frequency. The synchroscope pointer then turns slowly in the "fast" direction.
  4. Close the breaker as the pointer reaches the 12 o'clock position.
  5. Raise the governor setting of the incoming set until the sets share the active load (kW), then check the reactive load (kVAr).

The governors share the active load, and the AVRs share the reactive load. IACS Unified Requirement M3 sets the limits for the engine governors.

QuantityControlled byLimit in parallel operationSource
Active load (kW)GovernorsWithin 15% of the rated power of the largest set or 25% of the individual set, whichever is less, between 20% and 100% total loadIACS UR M3
Reactive load (kVAr)AVRsWithin 10% of the rated reactive output of the largest generator or 25% of the smallest, whichever is lessABS 4-8-3/3.13.3

What is the difference between a main generator and an emergency generator?

A main generator supplies the whole ship in normal service, and an emergency generator supplies only the safety services after the main supply fails. The emergency generator is an independent set with its own fuel tank, starting system and switchboard. The emergency generator stands above the uppermost continuous deck, outside the machinery casing.

AttributeMain generatorEmergency generator
LocationEngine room, near the main switchboardAbove the uppermost continuous deck, with access from the open deck
StartBy the crew or the power management systemAutomatic on loss of main power; on load in not more than 45 seconds
Supply periodContinuous18 hours for the listed services on cargo vessels of 500 GT and above (ABS); 36 hours for listed services on passenger ships (SOLAS II-1/42)
Cold startNo 0 °C ruleReady start at 0 °C, or heating is fitted
Stored starting energyStarting air or batteriesAt least three consecutive starts, plus a second source for three more starts within 30 minutes unless manual starting is effective

The 36-hour period for passenger ships is quoted in an IACS paper on SOLAS regulation II-1/42. Where one main generator normally carries the load, ABS requires a standby set to start and connect automatically after a blackout, in no case in more than 45 seconds.

What causes a ship generator to trip or fail?

A ship generator trips most often on reverse power, overload, overspeed or a loss of excitation. The protection opens the generator circuit breaker to protect the alternator and the other running sets. Most causes lie in the fuel system, the governor, the AVR or the winding insulation.

FaultCommon causeEffectAction
Reverse power tripEngine loses power in parallel operation: fuel starvation or governor faultThe alternator runs as a motor; the relay opens the breakerFind the engine fault before the set is reconnected
OverloadLoad exceeds the capacity of the running setsAutomatic load shedding of non-essential servicesStart another set; restore the shed loads in steps
Low or unstable voltageAVR fault, failed rectifier diode or loss of excitationUndervoltage trip; unequal kVAr sharingTest the AVR, the diodes and the exciter as the manual states
Low insulation resistanceMoisture, oil or dirt in the windingsEarth fault alarmClean and dry the windings; check the space heater

Work on a generator or a switchboard follows the ship's own procedures and the maker's manual.

Which ship generator spare parts are ordered most often?

Ship generator spare parts ordered most often are engine wear parts: fuel injection nozzles, fuel pump elements, piston rings, exhaust valves, main and big-end bearings, gasket sets and filters. Each cylinder liner and the marine turbocharger are renewed or overhauled at the hours stated in the engine manual. Alternator spares are bearings, AVR units and rectifier diodes.

A correct order states the following data:

  1. Ship name and IMO number.
  2. Engine maker, engine type and number of cylinders, for example 6L23/30H.
  3. Engine serial number from the nameplate.
  4. For alternator parts: alternator maker, type, serial number, kVA, voltage and frequency.
  5. Part number and plate number from the maker's spare parts book.

Gaskets, filters and other general consumables may carry an IMPA code. Engine and alternator components are ordered by the maker's part number.

Who makes ship generators and auxiliary engines?

Ship generators and auxiliary engines are made by a small group of engine builders and their licensees. Wärtsilä, Everllence (the former MAN Energy Solutions), Yanmar, Daihatsu Infinearth (the former Daihatsu Diesel) and HD Hyundai Heavy Industries, with the HiMSEN brand, are the names found most often on cargo ships.

  • Wärtsilä. Wärtsilä lists gensets from about 0.74 MW to 10.4 MW, based on the Wärtsilä 20, 25, 31 and 32 engines and dual-fuel versions.
  • Everllence. The Everllence GenSet range includes the L23/30H, the L21/31 and the L27/38. The maker states that more than 12,000 units of the L23/30H type have been installed.
  • Yanmar. The EY series includes the 6EY18 and the 6EY22.
  • Daihatsu Infinearth. The DE and DK series include the 6DE-18 and the 6DK-20e.
  • HD Hyundai Heavy Industries. The HiMSEN range includes the H21/32.

Where can ship generator parts be bought or sold?

Ship generator parts are bought from engine makers, licensed service companies and surplus stockists. MarineYard is a ship spare parts marketplace where sellers list new, reconditioned and used auxiliary engine parts and electrical and automation parts. Sellers get 9 free listings per account. MarineYard takes no commission and is not a party to any sale. Buyers should confirm the engine type, the serial number and the part number with the seller before payment.

Infographic on electrical power generation on ships: voltages and frequency, synchronising steps, load sharing limits and common trips
An emergency generator must take the load in not more than 45 seconds after the main power fails.

Frequently Asked Questions

How many generators does a ship have?

A ship has at least two generators for the main source of power, and many cargo ships carry three. Class rules require the remaining sets to carry the essential services with any one generator in reserve. An emergency generator is fitted in addition.

Why do ships use 440 V and 60 Hz?

Ships use 440 V and 60 Hz because both are recommended nominal values for three-phase ship systems in IEC 60092-201. The same standard lists 400 V for 50 Hz systems. Ships with a high electrical load use 6.6 kV or 11 kV, because a higher voltage means a lower current.

What does the AVR do on a ship generator?

The AVR on a ship generator holds the terminal voltage by adjusting the excitation current of the rotor. ABS rules require the AVR to keep the steady voltage within ±2.5% of rated voltage from no load to rated load. The AVRs also share the reactive load between sets in parallel.

What is reverse power in a ship generator?

Reverse power in a ship generator is a flow of active power from the busbars into the alternator. Reverse power occurs when the engine of one set in parallel loses power. A reverse power relay opens the breaker at 8% to 15% of rated power on diesel sets.

How fast must an emergency generator start on a ship?

An emergency generator on a ship must start automatically and supply the emergency switchboard in not more than 45 seconds after the main power fails. The set must start at 0 °C and must hold stored energy for at least three consecutive starts.

What is the difference between kW and kVA on a ship generator?

The kW rating of a ship generator is the active power that the engine can deliver through the alternator. The kVA rating is the apparent power of the alternator, which includes the reactive power. The kW value equals the kVA value multiplied by the power factor.

Related guides

Sources


Comments

Sign in to leave a comment and join the discussion.

9 Free Listings · No Credit Card Required

Got spare parts on board or in the warehouse?

List them on MarineYard and reach marine buyers worldwide — your first 9 listings are free.

9 free listingsNo credit card requiredNo commission on salesPremium plans: 7-day free trial